Cobblestone Inn & Suites is on the “Rise”

Check out the exciting progress.

Hotel progress is moving along quickly.
Here’s a pictorial timeline of the exciting news. – May 7, 2018

 

Parking lot gone in one day! Spent the weekend leveling dirt. Now the crew is putting in forms for the foundation footing. The Hotel is progressing so well, that the construction manager said they have never gone from ground zero to pouring foundation footings in one week! – May 14, 2018

 

Pouring footings now! – May 15, 2018

Getting water, sewer, wiring connections in place before foundation pouring! – May 21, 2018

 

All the connection for wiring, water, and sewage are done. The two foundation slabs have been poured and are drying. Up next…the framing will start soon! – June 6, 2018